66th Street & Portland Avenue

It is both the City’s and County’s responsibility to provide a safe and efficient transportation system.  The intersection at 66th Street and Portland Avenue has a history of severe crashes. 

Many residents recognize that confusion and delay problems exist at this intersection, but have expressed concern that major improvements are unnecessary and costly.  Some believe simply adding left turn arrows would solve the problems at the intersection.  Realistically, the addition of arrows could improve the safety of the intersection, but would result in increased delay and frustration already experienced by motorists.  The City has exhausted all possibilities of improving the conditions within the existing right-of-way. 

Two million dollars of federal funds have been allocated specifically to make safety improvements at this intersection.  To do nothing with these funds would not only be a lost opportunity to correct the problem, but would also be irresponsible on the part of City and County officials.

Before  Click to view larger image

Intersection at 66th and Portland before construction.

The intersection of 66th Street and Portland Avenue as it looks today and will look following construction. 

After  Click to view larger image

Intersection at 66th and Portland after construction.

 

Construction Timeline for 66th Street and Portland Avenue Roundabout
Including traffic impacts

Get a construction update by clicking here

Late March through Mid May 2008
Site preparation, including the demolition of the Mr. Tire, utility work which will include temporary lane closures.

Mid-May 2008
Temporary Pavements will be constructed for the construction staging.  Once the traffic control is in place, traffic will be reduced to one-lane in each direction, the signal will be removed and the intersection will operate as a single-lane roundabout.

Mid-October 2008
Construction is expected to be complete by mid-October.

Shafer Contracting Company is the project contractor and the timing of these operations is dependant on their schedule.