Construction on the 66th Street
and Portland Avenue Roundabout is underway.
August 13th Update
Lane changes will be taking place to allow for
removal of the old pavement and completion of underground
utility work. Oakland Avenue is temporally closed at 66th
Street during pavement removal. The bus detour on Park Avenue
from 66th to 67th Street will be moved to Elliot Avenue to allow
pavement removal and work to take place at Park Avenue and 66th
Street. The detour is set to begin Monday, August 13th
to coincide with pavement removal. This detour is expected to last
three to four weeks.
July 29th Update
The changeover to the temporary one lane
roundabout took place last Friday. Despite the rain,
everything went well. Concrete barriers and lane striping were
added to improve traffic flow. Changeable message signs were
moved closer to the intersection and messages were changed to inform
drivers. The one lane roundabout is working well, but we will
continue to monitor and make adjustments as necessary. The
dirt stockpiles should be removed this week and traffic will be
switched to the newly paved lanes. Removal of old pavement
will take place and underground work started once traffic has
switched. The bus detour will remain on 67th Street until
construction activities allow for the safe relocation of the bus
stops on 66th Street.
July 22nd Update
UPDATE - Plans for
the changeover to the temporary one lane roundabout have been moved
up to Friday, July 26th, after the morning rush hour. The
changeover should be completed and open to traffic in time for the
evening rush hour. There will be no closure of the
intersection, it will remain open during the change, but there may
be short term delays during the day. The signal will be
disconnected and removed at this time. Changeable message
signs are in place and will be used to inform drivers to stop for
traffic in the Roundabout.
Starting Wednesday, July 23rd, permanent and
temporary paving will be taking place in preparation for the traffic
changeover. Paving should be complete by Thursday.
July 15th Update
A lot of changes will take place in the coming
week. Paving of the
east side of Portland Avenue and the north side of 66th Street will
take place next
week. Current plans are to have the signal disconnected early morning Saturday, July 27th when the
intersection will change over to the temporary 1 lane roundabout.
A short term closure of the intersection is planned for 5-7am
Saturday, July 27th. Plans are dependant on weather and subject
to change, please refer to this website for the latest updates.
July 8th Update
Temporary fencing for the 4th of July
celebration was removed, everything went well on the 4th.
Removal of the remaining portion of NB Portland is taking place.
Curb and gutter is going in on the south side of 66th Street and the
east side of Portland Avenue. Street light bases are going in
on portions of the project.
July 1st Update
The bus route change took place on June 27th.
Subcut excavation and filling with select granular and class 5 is
taking place on the south leg of northbound Portland Avenue and the west
leg of westbound 66th Street . Site clean up and temporary fencing
is going in for the 4th of July. Curb and gutter is scheduled
for next week for portions of the NE corner of the project.
Most of the power poles have now been removed and the utilities have
been buried underground.
June 24th Update
Due to traffic
congestion from buses entering and exiting the construction site at
66th Street and 5th Avenue, Metro Transit Buses will be rerouted
from 66th to 67th Street between Nicollet and Park Avenue. This
change is scheduled to take place on Friday, June 27th after the
morning rush hour. We will continue to work to get all Metro
Transit Buses back onto 66th Street when construction activities
allow for the safe relocation of the bus stops.
At this time, the
changeover from the signalized intersection to the temporary single
lane roundabout is anticipated to take place around the end of
July. Work done by the City’s contractor continues to be delayed
due to relocation of private utilities. The City and contractor are
working to create a safe construction site for the 4th of July
Celebration.